Start Date End Date Phase Task Responsible Status
11/10/2007 12/21/2007 I Hire new telecom technician Kelly DONE
1/3/2008 3/31/2008 I Creation of user training/documentation Hinz DONE
1/7/2008 2/29/2008 I Verification of timeline for cutover Quiner/Callister DONE
1/8/2008 1/10/2008 I Installation and testing of Billing Software Kelly/Hubbard/Quiner DONE
1/8/2008 1/9/2008 I Install sample 7911G, 7941G, and 7961G phones Hubbard/Morales DONE
1/14/2008 5/1/2008 VI Identify locations for the PA system and classroom phones Rogers/Hubbard DONE
1/16/2008 1/16/2008 I Upgrade to Unity Connections version 2.0 Hubbard/Morales DONE
1/23/2008 2/24/2008 I Call Manager Upgrade to version 6.1 Hubbard DONE
1/24/2008 2/5/2008 I Install VG224 to convert 16 modem lines to VoIP Hubbard DONE
2/1/2008 2/29/2008 I Verification of desktop unit model Quiner/Callister DONE
2/4/2008 2/29/2008 I Install 2nd T1 trunk from Quest  Hubbard DONE
2/4/2008 5/1/2008 I Install of CAMA trunk and E911 service
Install Cisco Emergency Responder for E911 service
Hubbard/Morales 20%
2/4/2008 2/29/2008 I Installation & Configuration of 2nd Call Manager Hubbard DONE
2/4/2008 3/7/2008 I Installation and testing of VoIP troubleshooting/diagnosis platform Hubbard DONE
3/3/2008 3/3/2008 II Order Desk sets for administrative offices Kelly/Hubbard DONE
3/8/2008 3/8/2008 I Installation of two new Server Racks Kelly/Hubbard/Morales DONE
3/10/2008 3/14/2008 I Voice Rewiring/Wall Plate changes in Olin, North, Science and Maxey Hubbard/Morales DONE
3/17/2008 3/21/2008 I VoIP training for WCTS support staff Hinz DONE
3/17/2008 3/21/2008 I VoIP training for new Telecom Technician Morales DONE
3/17/2008 5/1/2008 II, V Install POTS for offices scheduled for April installation Qwest/Hubbard DONE
3/24/2008 3/28/2008 I Call Manager and Unity integration with LDAP Osterman DONE
3/31/2008 4/4/2008 II Training for Alumni House, Penrose House, BFC, Cordiner Hall Hinz DONE
3/31/2008 4/4/2008 II Training for Welty Welness Center Hinz DONE
4/1/2008 4/3/2008 I Installation VoIP switch and QoS setup in Memorial Kelly/Hubbard/Morales DONE
4/4/2008 4/7/2008 III Order Desk sets for Academic buildings Kelly/Hubbard DONE
4/7/2008 4/11/2008 II Training for Business Office Hinz DONE
4/7/2008 4/7/2008 II Alumni House setups Hubbard/Morales/Kelly DONE
4/7/2008 4/7/2008 II Alumni House cutover at 5:00 PM Qwest/Hubbard DONE
4/7/2008 4/7/2008 II Deploy Alumni House VoIP phones Hubbard/Morales DONE
4/7/2008 4/7/2008 II BFC/Cordiner cutover at 5:00 PM Qwest/Hubbard DONE
4/8/2008 4/8/2008 II Setup & Deploy BFC and Cordiner VoIP phones Hubbard/Morales DONE
4/8/2008 4/9/2008 II Wellness Center setups Hubbard/Morales/Kelly DONE
4/10/2008 4/10/2008 II Wellness Center cutover at 5:00 PM Qwest/Hubbard DONE
4/9/2008 4/9/2008 II Deploy Wellness Center VoIP phones Hubbard/Morales DONE
4/9/2008 4/9/2008 II Training for Development and Alumni Fund Hinz DONE
4/11/2008 4/14/2008 II Business Office setups Hubbard/Morales/Kelly DONE
4/14/2008 4/14/2008 II Business Office cutover at 7:00 AM and 5:00 PM Qwest/Hubbard DONE
4/14/2008 4/15/2008 II Deploy Business Office VoIP phones Hubbard/Morales DONE
4/14/2008 4/18/2008 II Training for Office of the President, Dean of Students and Dean of Faculty Hinz DONE
4/15/2008 4/15/2008 II Development setups Hubbard/Morales/Kelly DONE
4/15/2008 4/15/2008 II Development cutover at 5:00 PM Qwest/Hubbard DONE
4/16/2008 4/16/2008 II Training for Communications/Production Services Hinz DONE
4/16/2008 4/16/2008 II Deploy Development VoIP phones Hubbard/Morales DONE
4/17/2008 5/31/2008 II Install POTS for offices scheduled for May installation Qwest/Hubbard DONE
4/18/2008 4/18/2008 II Phone-a-thon room cutover at 7:00 AM Qwest/Hubbard DONE
4/18/2008 4/18/2008 II Setup & Deploy Phone-a-thon room VoIP phones Hubbard/Morales/Kelly DONE
4/18/2008 4/18/2008 II Install 3rd trunk line in North Hall Hubbard DONE
4/20/2008 4/20/2008 II Setups for Office of the President and Dean of Faculty Hubbard/Morales/Kelly DONE
4/21/2008 4/21/2008 II Office of Pres/Dean of Faculty cutover at 7:00 AM Qwest/Hubbard DONE
4/21/2008 4/21/2008 II Deploy VoIP phones in Office of the President and Dean of Faculty Hubbard/Morales DONE
4/21/2008 4/25/2008 II Training for Penrose Library Hinz DONE
4/21/2008 4/21/2008 II Setup for Communication (Mem) and Production Services (Boyer) Hubbard/Morales/Kelly DONE
4/22/2008 4/22/2008 II Communication & Production Cutover at 7:00 AM Qwest/Hubbard DONE
4/22/2008 4/22/2008 II Deploy Communication & Production Services VoIP phones Hubbard/Morales DONE
4/28/2008 4/29/2008 II Training for Penrose House (Admission & Fin Aid) Hinz DONE
4/25/2008 8/15/2008 II Sherwood House cutover  Qwest/Hubbard pending
4/25/2008 8/15/2008 II Setup & Deploy Sherwood House VoIP phones Hubbard/Morales/Kelly pending
4/28/2008 5/2/2008 II Training for Registrar, Academic Resources Center, Bon Appetite and Plant Services Hinz DONE
4/30/2008 4/30/2008 II Penrose Library setups Hubbard/Morales/Kelly DONE
5/1/2008 5/1/2008 II Penrose Library cutover at 7:00 AM Qwest/Hubbard DONE
5/1/2008 5/1/2008 II Deploy Penrose Library VoIP phones Hubbard/Morales DONE
5/1/2008 5/1/2008 II Penrose House setups Hubbard/Morales/Kelly DONE
5/2/2008 5/2/2008 II Penrose House cutover at 7:00 AM Qwest/Hubbard DONE
5/2/2008 5/2/2008 II Deploy Penrose House VoIP phones Hubbard/Morales DONE
5/2/2008 5/2/2008 II Install 4th T1 trunk in Prentiss Hubbard DONE
5/2/2008 5/2/2008 IV Order VG224 units for Residence Halls Kelly/Hubbard DONE
5/2/2008 5/2/2008 II Setup for Dean of Students Hubbard/Morales/Kelly DONE
5/5/2008 5/5/2008 II Registrar and Academic Resources cutover at 7:00 AM Qwest/Hubbard DONE
5/5/2008 5/5/2008 II Setup & Deploy Registrar and Academic Resource Center VoIP phones Hubbard/Morales DONE
5/5/2008 5/5/2008 II Dean of Student cutover at 7:00 AM  Qwest/Hubbard DONE
5/5/2008 5/5/2008 II Deploy Dean of Students VoIP phones Hubbard/Morales DONE
5/5/2008 5/5/2008 II Bon Appetite setups in Jewett and Prentiss Hubbard/Morales/Kelly DONE
5/6/2008 5/6/2008 II Bon Appetite cutover at 7:00 AM Qwest/Hubbard DONE
5/6/2008 5/6/2008 II Deploy Bon Appetite VoIP phones Hubbard/Morales DONE
5/7/2008 5/7/2008 II Plant Services setup Hubbard/Morales/Kelly DONE
5/8/2008 5/8/2008 II Plant Services cutover at 7:00 AM Qwest/Hubbard DONE
5/8/2008 5/8/2008 II Deploy Plant Services VoIP phones Hubbard/Morales DONE
5/11/2008 5/13/2008 II Reid Campus Center setups (All floors) Hubbard/Morales/Kelly DONE
5/12/2008 5/12/2008 II Reid Campus Center 2nd flr cutover at 7:00 AM Qwest/Hubbard DONE
5/12/2008 5/12/2008 II Deploy Reid 2nd flr VoIP phones  Hubbard/Morales DONE
5/12/2008 8/15/2008 III Training Classes for Academics Hinz on-oing
5/13/2008 5/13/2008 II Reid Campus Center 1st floor cutover at 7:00 AM Qwest/Hubbard DONE
5/13/2008 5/13/2008 II Deploy Reid 1st flr VoIP phones  Hubbard/Morales DONE
5/14/2008 5/14/2008 II Reid Campus Center – remaining floors cutover at 7:00 AM Qwest/Hubbard DONE
5/14/2008 5/14/2008 II Deploy Reid (remaining) VoIP phones Hubbard/Morales DONE
5/14/2008 5/14/2008 II Human Resources and Security setups Hubbard/Morales/Kelly DONE
5/15/2008 5/15/2008 II Human Resources and Security cutover at 7:00 AM Qwest/Hubbard DONE
5/15/2008 5/15/2008 II Deploy Human Resources and Security VoIP phones Hubbard/Morales DONE
5/19/2008 5/19/2008 III Hunter setups Hubbard/Morales/Kelly DONE
5/20/2008 5/20/2008 III Hunter cutover at 7:00 AM Qwest/Hubbard DONE
5/20/2008 5/20/2008 III Deploy Hunter VoIP phones Hubbard/Morales DONE
5/21/2008 5/21/2008 III Dance Studio setups Hubbard/Morales/Kelly DONE
5/21/2008 5/21/2008 III Harper Joy Theatre setups Hubbard/Morales/Kelly DONE
5/22/2008 5/22/2008 III Dance Studio cutover at 7:00 AM Qwest/Hubbard DONE
5/22/2008 5/22/2008 III Harper Joy Theatre cutover at 7:00 AM Qwest/Hubbard DONE
5/22/2008 5/22/2008 II Res Life cutover at 7:00 AM Qwest/Hubbard DONE
5/22/2008 5/22/2008 II Setup and Deploy Res Life VoIP phones Hubbard/Morales DONE
5/22/2008 5/22/2008 III Deploy Dance Studio VoIP phones Hubbard/Morales DONE
5/22/2008 5/22/2008 III Deploy Harper Joy Theatre VoIP phones Hubbard/Morales DONE
5/27/2008 5/27/2008 III Baker Ferguson Fitness Center setups Hubbard/Morales/Kelly DONE
5/28/2008 5/28/2008 III BFFC cutover at 7:00 AM Qwest/Hubbard DONE
5/28/2008 5/28/2008 III Deploy Baker Ferguson Fitness Center VoIP phones Hubbard/Morales DONE
5/29/2008 5/29/2008 III Boyer House setups Hubbard/Morales/Kelly DONE
5/30/2008 5/30/2008 III Boyer House cutover at 7:00 AM Qwest/Hubbard DONE
5/30/2008 5/30/2008 III Deploy Boyer House VoIP phones Hubbard/Morales DONE
6/2/2008 6/30/2008 III Install POTS lines in division offices Qwest/Hubbard DONE
6/2/2008 6/2/2008 III Maxey Hall setups Hubbard/Morales/Kelly DONE
6/2/2008 8/29/2008 VI Install wiring and classroom phones Walla Walla Electric/ Hubbard 80%
6/3/2008 6/3/2008 III Maxey Hall cutover at 7:00 AM Qwest/Hubbard DONE
6/3/2008 6/4/2008 III Deploy Maxey Hall VoIP phones Hubbard/Morales DONE
6/5/2008 6/5/2008 III Hall of Music setups Hubbard/Morales/Kelly DONE
6/6/2008 6/6/2008 III Hall of Music cutover at 7:00 AM Qwest/Hubbard DONE
6/6/2008 6/6/2008 III Deploy Hall of Music VoIP phones Hubbard/Morales DONE
6/9/2008 6/10/2008 III Olin Hall setups Hubbard/Morales/Kelly DONE
6/11/2008 6/11/2008 III Olin Hall 1st flr cutover at 7:00 AM Qwest/Hubbard DONE
6/11/2008 6/11/2008 III Deploy Olin Hall 1st flr VoIP phones  Hubbard/Morales DONE
6/12/2008 6/12/2008 III Olin Hall 2nd flr cutover at 7:00 AM Qwest/Hubbard DONE
6/12/2008 6/12/2008 III Deploy Olin Hall 2nd flr VoIP phones  Hubbard/Morales DONE
6/13/2008 6/13/2008 III Olin Hall 3rd flr cutover at 7:00 AM Qwest/Hubbard DONE
6/13/2008 6/13/2008 III Deploy Olin Hall 3rd flr VoIP phones  Hubbard/Morales DONE
6/16/2008 6/16/2008 III Hall of Science setups Hubbard/Morales/Kelly DONE
6/17/2008 6/17/2008 III Hall of Science 1st flr cutover at 7:00 AM Qwest/Hubbard DONE
6/17/2008 6/17/2008 III Deploy Hall of Science 1st flr  VoIP phones  Hubbard/Morales DONE
6/18/2008 6/18/2008 III Hall of Science 2nd flr cutover at 7:00 AM Qwest/Hubbard DONE
6/18/2008 6/18/2008 III Deploy Hall of Science 2nd flr VoIP phones  Hubbard/Morales DONE
6/19/2008 6/19/2008 III Hall of Science 3rd flr cutover at 7:00 AM Qwest/Hubbard DONE
6/19/2008 6/19/2008 III Deploy Hall of Science 3rd flr VoIP phones  Hubbard/Morales DONE
6/19/2008 6/19/2008 III Sherwood Center setups Hubbard/Morales/Kelly pending
6/20/2008 6/20/2008 III Sherwood Center cutover at 7:00 AM Qwest/Hubbard pending
6/20/2008 6/20/2008 III Deploy Sherwood Center VoIP phones Hubbard/Morales pending
6/23/2008 6/24/2008 IV Jewett Hall setups Hubbard/Morales/Kelly DONE
6/25/2008 6/25/2008 IV Jewett Hall 1st flr cutover at 7:00 AM Qwest/Hubbard DONE
6/25/2008 6/25/2008 IV Deploy Jewett Hall 1st flr  phones  Hubbard/Morales DONE
6/26/2008 6/26/2008 IV Jewett Hall 2nd flr cutover at 7:00 AM Qwest/Hubbard DONE
6/26/2008 6/26/2008 IV Deploy Jewett Hall 2nd flr phones  Hubbard/Morales DONE
6/27/2008 6/27/2008 IV Jewett Hall 3rd flr cutover at 7:00 AM Qwest/Hubbard DONE
6/27/2008 6/27/2008 IV Deploy Jewett Hall 3rd flr phones  Hubbard/Morales DONE
6/30/2008 6/30/2008 IV Jewett Hall 4th flr cutover at 7:00 AM Qwest/Hubbard DONE
6/30/2008 6/30/2008 IV Deploy Jewett Hall 4th flr phones  Hubbard/Morales DONE
7/1/2008 7/7/2008 IV Prentiss Hall setups Hubbard/Morales/Kelly DONE
7/8/2008 7/8/2008 IV Prentiss Hall 1st flr cutover at 7:00 AM Qwest/Hubbard DONE
7/8/2008 7/8/2008 IV Deploy Prentiss Hall 1st flr phones  Hubbard/Morales DONE
7/9/2008 7/9/2008 IV Prentiss Hall 2nd flr cutover at 7:00 AM Qwest/Hubbard DONE
7/9/2008 7/9/2008 IV Deploy Prentiss Hall 2nd flr phones  Hubbard/Morales DONE
7/10/2008 7/10/2008 IV Prentiss Hall 3rd flr cutover at 7:00 AM Qwest/Hubbard DONE
7/10/2008 7/10/2008 IV Deploy Prentiss Hall 3rd flr phones  Hubbard/Morales DONE
7/11/2008 7/11/2008 IV Douglas Hall setups Hubbard/Morales/Kelly DONE
7/14/2008 7/14/2008 IV Douglas Hall cutover at 7:00 AM Qwest/Hubbard DONE
7/14/2008 7/15/2008 IV Deploy Douglas Hall phones Hubbard/Morales DONE
7/16/2008 7/16/2008 IV Lyman Hall setups Hubbard/Morales/Kelly DONE
7/17/2008 7/17/2008 IV Lyman Hall cutover at 7?00 AM Qwest/Hubbard DONE
7/17/2008 7/17/2008 IV Deploy Lyman Hall phones Hubbard/Morales DONE
7/21/2008 7/22/2008 IV Anderson Hall setups Hubbard/Morales/Kelly DONE
7/23/2008 7/23/2008 IV Anderson Hall 1st flr cutover at 7:00 AM Qwest/Hubbard DONE
7/23/2008 7/23/2008 IV Deploy Anderson Hall 1st flr phones  Hubbard/Morales DONE
7/24/2008 7/24/2008 IV Anderson Hall 2nd flr cutover at 7:00 AM Qwest/Hubbard DONE
7/24/2008 7/24/2008 IV Deploy Anderson Hall  2nd flr phones  Hubbard/Morales DONE
7/25/2008 7/25/2008 IV Anderson Hall 3rd flr cutover at 7:00 AM Qwest/Hubbard DONE
7/25/2008 7/25/2008 IV Deploy Anderson Hall 3rd flr phones  Hubbard/Morales DONE
7/28/2008 7/29/2008 IV North Hall setups Hubbard/Morales/Kelly DONE
7/30/2008 7/30/2008 IV North Hall 1st flr cutover at 7:00 AM Qwest/Hubbard DONE
7/30/2008 7/30/2008 IV Deploy North Hall 1st flr phones  Hubbard/Morales DONE
7/31/2008 7/31/2008 IV North Hall 2nd flr cutover at 7:00 AM Qwest/Hubbard DONE
7/31/2008 7/31/2008 IV Deploy North Hall 2nd flr phones  Hubbard/Morales DONE
8/1/2008 8/1/2008 IV North Hall 3rd flr cutover at 7:00 AM Qwest/Hubbard DONE
8/1/2008 8/1/2008 IV Deploy North Hall 3rd flr phones  Hubbard/Morales DONE
8/1/2008 8/1/2008   Center for Visual Arts installations Hubbard/Morales DONE
8/4/2008 8/4/2008 IV College House setups Hubbard/Morales/Kelly  
8/5/2008 8/5/2008 IV College House cutover at 7:00 AM Qwest/Hubbard  
8/5/2008 8/5/2008 IV Deploy College House phones Hubbard/Morales  
8/6/2008 8/6/2008 IV Marcus House setups Hubbard/Morales/Kelly  
8/7/2008 8/7/2008 IV Marcus House cutover at 7:00 AM Qwest/Hubbard  
8/7/2008 8/7/2008 IV Deploy Marcus House phones Hubbard/Morales  
8/8/2008 8/8/2008 IV Tamarac House cutover at 7:00 AM Qwest/Hubbard  
8/8/2008 8/8/2008 IV Setup & Deploy Tamarac House phones Hubbard/Morales  
8/11/2008 8/22/2008 V Install POTS lines in Residence Halls Qwest/Hubbard  
9/1/2008 10/30/2008