IMPLEMENTATION PROJECT TEAM
September 8, 2000


Attending: Jenny Miles, Cindy Waring, Varga Fox, Jim Ply, Walter Froese, Jed Schwendiman, Nellie Newer, Susan Healy

Financial Aid

  • Ready to start data conversion on Monday. Working toward Sept 27 live date.

Residence Life

  • All addresses have been entered for off-campus students.
  • Start looking at roommate matching & lottery next week.

Registrar

  • Survived registration with a certain amount of style and grace.
  • Encountering problems in add/drop period with AR, overload checking, required labs, room conflicts.
  • Rather concerned about getting transcript program from Datatel in time - Datatel has been working on it since February.

HR/Payroll

  • Had a consultant from Datatel for 2 days this week. Found it very helpful. More work ahead - process mapping/improvement, training and consulting.
  • Walter wants to streamline timesheet entry - feels they are spending too much time in this area.

Business Office

  • Want to get a purchasing and travel card (to replace AmEx) and integrate it into Datatel somehow.
  • Having difficulties with selecting vendors to pay.
  • Starting to move balances from legacy to Colleague so will have budget reports available.

AR

  • Problem with cash receipts not showing in the system when you select by term on ARIQ, ARAI. Only the charges show. Everything shows if you don't enter a term.
  • Deferred payment plan statement still needs some work.
  • Issues with finance charges not working as they should.