ConnectED Implementation Schedule
Dates Phase Tasks Staff  Status
10/3/2007 Setup Purchase Service Osterman Completed
11/12/2007 Setup Configure ConnectED site Osterman Completed
11/27/2007 Setup Load Test ConnectED contacts Quiner Completed
11/29/2007 Setup ConnectED training Quiner, Osterna, Hinz, Rogers, Wardell Completed
11/30/2007 Setup Prepare datatel/ConnectED scripts Quiner Completed
12/7/2007 Implementation Load data from existing Datatel data Quiner Completed
1/5/2008 Implementation Collect and load additional data fromWCTS staff Quiner Completed
1/5/2008 Test Pre-notify and send test messages to the WCTS group Quiner Completed
1/5/2008 Implementation Load additional information for staff on the White Card  Quiner Completed
1/7/2008 - 1/14/2008 Implementation Collect Students emergency phone number (cell) information Quiner Completed
1/29/2008 Test Pre-notify and send test messages to the Implementation Team (Rogers, Wardwell, Hinz, Quiner, Osterman) Wardwell, Rogers, Quiner Completed
1/29/2008 Implementation Collect additioanl data for members of the Directors Round Table (the Directors group) Quiner Completed
1/29/2008 Test Pre-notify the Directors group of test message Quiner Completed
1/30/2008 Implementation Meet and demo (send test msg) to Directors Round Table - 8:30 am Wardwell, Rogers, Quiner Completed
1/31/2008 Setup Develop form for people to submit their emergency contact info Hinz,Quiner Completed
1/31/2008 Implementation Load Students emergency phone number (cell) information Quiner Completed
1/31/2008 Test Pre-notify and send test msg to the White Card group Wardwell, Rogers, Quiner Completed
2/4/2008 Milestone NOTIFICATION READY: the Whitecard group and the Director Group    Completed
2/4/2008 Implementation Send memo to staff re ConnectED Wardwell Completed
2/6/2008 - 2/11/2008 Implementation Collect additional data from staff Hinz Completed
2/12/2008 Implementation Load staff data Quiner Completed
2/12/2008 Test Pre-notify and send test msg to the Staff group Wardwell, Rogers, Quiner Completed
2/12/2008 Implementation Send memo to faculty re ConnectED Wardwell   Completed
2/13/2008 - 2/18/2008 Implementation Collect additional faculty information HInz Completed
2/15/2008 Implementation Prepare Standard Notification Messages Wardwell, Rogers Completed
2/15/2008 Implementation Develop activation guidelines and Protocols Wardwell, Rogers In Progress
2/15/2008 Implementation Training for Activation group Quiner, Hinz, Wardwell Completed
2/25/2008 Milestone NOTIFICATION READY: the Staff group   Completed
3/14/2008 Implementation Send memo to students re ConnectED Wardwell Completed
3/5/2008 Test Pre-notify and send test msg to the Faculty group Wardwell, Rogers, Quiner Completed
3/15/2008 Milestone NOTIFICATION READY: the Faculty group   Completed
3/26/2008 Test Pre-notify and send test msg to the Student Group Wardwell, Rogers, Quiner Completed
4/2/2008 Milestone NOTIFICATION READY: the Student group   Completed
2/13/2008 - 5/15/2008 Implementation Collect Trustee information Quiner Completed
5/15/2008 Test Pre-notify and send test msg to the Trustee group Wardwell, Rogers, Quiner  
7/1/2008 Implementation Send memo to Parents re ConnectED Wardwell  
7/8/2008-8/1/2008 Implementation Collect Parents info Quiner  
8/7/2008 Implementation Load parents information Quiner  
8/8/2008 Test Pre-notify and send test msg to the Parents group Wardwell, Rogers, Quiner  
8/18/2008 Milestone NOTIFICATION READY: the Parents Group