| ConnectED Implementation Schedule | ||||
| Dates | Phase | Tasks | Staff | Status |
| 10/3/2007 | Setup | Purchase Service | Osterman | Completed |
| 11/12/2007 | Setup | Configure ConnectED site | Osterman | Completed |
| 11/27/2007 | Setup | Load Test ConnectED contacts | Quiner | Completed |
| 11/29/2007 | Setup | ConnectED training | Quiner, Osterna, Hinz, Rogers, Wardell | Completed |
| 11/30/2007 | Setup | Prepare datatel/ConnectED scripts | Quiner | Completed |
| 12/7/2007 | Implementation | Load data from existing Datatel data | Quiner | Completed |
| 1/5/2008 | Implementation | Collect and load additional data fromWCTS staff | Quiner | Completed |
| 1/5/2008 | Test | Pre-notify and send test messages to the WCTS group | Quiner | Completed |
| 1/5/2008 | Implementation | Load additional information for staff on the White Card | Quiner | Completed |
| 1/7/2008 - 1/14/2008 | Implementation | Collect Students emergency phone number (cell) information | Quiner | Completed |
| 1/29/2008 | Test | Pre-notify and send test messages to the Implementation Team (Rogers, Wardwell, Hinz, Quiner, Osterman) | Wardwell, Rogers, Quiner | Completed |
| 1/29/2008 | Implementation | Collect additioanl data for members of the Directors Round Table (the Directors group) | Quiner | Completed |
| 1/29/2008 | Test | Pre-notify the Directors group of test message | Quiner | Completed |
| 1/30/2008 | Implementation | Meet and demo (send test msg) to Directors Round Table - 8:30 am | Wardwell, Rogers, Quiner | Completed |
| 1/31/2008 | Setup | Develop form for people to submit their emergency contact info | Hinz,Quiner | Completed |
| 1/31/2008 | Implementation | Load Students emergency phone number (cell) information | Quiner | Completed |
| 1/31/2008 | Test | Pre-notify and send test msg to the White Card group | Wardwell, Rogers, Quiner | Completed |
| 2/4/2008 | Milestone | NOTIFICATION READY: the Whitecard group and the Director Group | Completed | |
| 2/4/2008 | Implementation | Send memo to staff re ConnectED | Wardwell | Completed |
| 2/6/2008 - 2/11/2008 | Implementation | Collect additional data from staff | Hinz | Completed |
| 2/12/2008 | Implementation | Load staff data | Quiner | Completed |
| 2/12/2008 | Test | Pre-notify and send test msg to the Staff group | Wardwell, Rogers, Quiner | Completed |
| 2/12/2008 | Implementation | Send memo to faculty re ConnectED | Wardwell | Completed |
| 2/13/2008 - 2/18/2008 | Implementation | Collect additional faculty information | HInz | Completed |
| 2/15/2008 | Implementation | Prepare Standard Notification Messages | Wardwell, Rogers | Completed |
| 2/15/2008 | Implementation | Develop activation guidelines and Protocols | Wardwell, Rogers | In Progress |
| 2/15/2008 | Implementation | Training for Activation group | Quiner, Hinz, Wardwell | Completed |
| 2/25/2008 | Milestone | NOTIFICATION READY: the Staff group | Completed | |
| 3/14/2008 | Implementation | Send memo to students re ConnectED | Wardwell | Completed |
| 3/5/2008 | Test | Pre-notify and send test msg to the Faculty group | Wardwell, Rogers, Quiner | Completed |
| 3/15/2008 | Milestone | NOTIFICATION READY: the Faculty group | Completed | |
| 3/26/2008 | Test | Pre-notify and send test msg to the Student Group | Wardwell, Rogers, Quiner | Completed |
| 4/2/2008 | Milestone | NOTIFICATION READY: the Student group | Completed | |
| 2/13/2008 - 5/15/2008 | Implementation | Collect Trustee information | Quiner | Completed |
| 5/15/2008 | Test | Pre-notify and send test msg to the Trustee group | Wardwell, Rogers, Quiner | |
| 7/1/2008 | Implementation | Send memo to Parents re ConnectED | Wardwell | |
| 7/8/2008-8/1/2008 | Implementation | Collect Parents info | Quiner | |
| 8/7/2008 | Implementation | Load parents information | Quiner | |
| 8/8/2008 | Test | Pre-notify and send test msg to the Parents group | Wardwell, Rogers, Quiner | |
| 8/18/2008 | Milestone | NOTIFICATION READY: the Parents Group | ||